Hon. Tjorn Sibma questions the Minister for Transport regarding the completion of testing, driver training, and the opening date of the delayed Forrestfield-Airport Link. The Minister's response is non-committal, stating completion depends on successful testing.

AnsweredQoN 387Legislative Council
Asked
11 May 2022
Portfolio
Transport

QuestionView source ↗

FORRESTFIELD–AIRPORT
LINK — COMMENCEMENT
387. Hon TJORN SIBMA to the Leader of the House representing
the Minister for Transport:
I
refer to the minister's answer yesterday concerning the commencement of
services on the Forrestfield–Airport Link.
(1) When will the current testing
and commissioning work be complete?
(2) When will train driver training
commence and conclude?
(3) Will the already much delayed
link open before the end of June?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1)–(3) Given
the very nature of the testing and commissioning phase, it will finish when all
tests have been successfully passed. Driver training will commence once the
airport line has completed testing and commissioning.