Details the expenditure on works at the Mandurah and Nowergup depots as part of the Butler rail extension project, totalling $38.66 million of the $240 million budget.

AnsweredQoN 2533Legislative Council
Asked
17 February 2015
Portfolio
Transport

QuestionView source ↗

How much of the $240 million budget for the Butler rail extension was spent on: (a) works at the Mandurah Depot and what were the works; and (b) works at the Nowergup Depot and what were the works?

AnswerView source ↗

Answered
17 March 2015
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
28 days
(a) $11.61 million has been spent on works at the Mandurah Depot. These works are:
· Track works, overhead line works, civil works and signalling works to expand capacity.
· Provision of railcar inspection and cleaning facilities.
(b) $27.05 million has been spent on works at Nowergup Depot. These works are:
· Track works, overhead line works, civil works, signalling, communications and electrical works to expand capacity and improve operational flexibility.
· Provision of a new arch underpass and access road into the depot.
· Provision of new security fencing at the depot.