❓ Question regarding the commencement and completion dates of public boat ramp upgrades at Tantabiddi and Bundegi, and the allocated funding for each. The Minister's response indicates project management is handled by the Shire of Exmouth, with construction anticipated in early 2007 and funding details dependent on design.
AnsweredQoN 495Legislative Council
QuestionView source ↗
PUBLIC BOAT RAMPS - EXMOUTH
I refer to the upgrading of the public boat ramps at Tantabiddi and Bundegi to improve access to Exmouth waters, listed as a major initiative in the 2006-07 budget. (1) When will construction commence, and what is the anticipated completion date of each ramp? (2) How much funding has been allocated for each ramp? Hon ADELE FARINA
I refer to the upgrading of the public boat ramps at Tantabiddi and Bundegi to improve access to Exmouth waters, listed as a major initiative in the 2006-07 budget. (1) When will construction commence, and what is the anticipated completion date of each ramp? (2) How much funding has been allocated for each ramp? Hon ADELE FARINA
AnswerView source ↗
I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(1) When will construction commence, and what is the anticipated completion date of each ramp? (2) How much funding has been allocated for each ramp? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(2) How much funding has been allocated for each ramp? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(1) When will construction commence, and what is the anticipated completion date of each ramp? (2) How much funding has been allocated for each ramp? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(2) How much funding has been allocated for each ramp? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
I thank the member for some notice of this question. (1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(1) The Shire of Exmouth is responsible for project managing these works with funding allocated from the state budget. Construction at Bundegi is anticipated in early 2007, followed by construction at Tantabiddi. (2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
(2) The break-up of the funding of $1.5 million is subject to the detailed design of each ramp, and it is being managed by the shire.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.