Ms. Mettam inquires about the status of the Cape Naturaliste College expansion project announced in the 2016-17 budget. The Minister provides a timeline for the tender process, construction commencement, and expected completion dates for various stages of the project.

AnsweredQoN 1664Legislative Assembly
Asked
8 August 2017
Portfolio
Education and Training

QuestionView source ↗

What is the current status of the $32.1 million second stage of Cape Naturaliste College's expansion announced by the previous Government in the 2016-17 State Budget: (a) are building works on schedule to commence in 2018; and (b) what is the expected completion date of the second stage of Cape Naturaliste College's expansion?

AnswerView source ↗

Answered
12 September 2017
Responded by
Minister representing the Minister for Education and Training
Response time
9 days
With regard to the second stage of expansion works, a Request for Tender is expected to be issued in November 2017, with the tender awarded in February 2018 and construction scheduled to commence in March 2018.
(a)        Yes.
(b)       New buildings are anticipated to be completed by May 2019. Converted areas are planned to be completed by October 2019. The removal of transportable classrooms and provision of new car parking and landscape is estimated to be completed by December 2019.