❓ A WA parliamentary question addresses the Department of Environment regarding the fulfillment of a condition related to land remediation for a subdivision in Landsdale. The response indicates that additional information is required from the developer before the condition can be considered fulfilled.
AnsweredQoN 625Legislative Council
QuestionView source ↗
I refer to a letter to Greg Rowe and Associates from the Western Australian Planning Commission in relation to the approval for subdivision of lots 22, 23 and 24 Kingsway Road, Landsdale, dated 1 October 2004. In particular I refer to point 19, relating to approval of the plan of survey for those lots, which states that a site remediation and validation report from the subject land must be prepared by the subdivider prior to the commencement of the earthworks at the subdivider’s cost, and that remediation works must be undertaken at the subdivider’s cost for all identified contamination and should be validated as being free of contamination above accepted guidelines to the satisfaction of the Western Australia Planning Commission. (1) Has the Land and Water Quality Branch of the Department of Environment received two reports, carried out by MPL Pty Ltd, in relation to the subdivision of lots 22, 23 and 24 Kingsway Road, Landsdale? (2) If yes, based upon these reports, will the Department of Environment confirm that condition 19 in relation to lots 22, 23 and 24 Kingsway Road, Landsdale has been fulfilled? If so, when will notification of approval be provided to the Western Australian Planning Commission? Hon LJILJANNA RAVLICH
AnswerView source ↗
I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(1) Has the Land and Water Quality Branch of the Department of Environment received two reports, carried out by MPL Pty Ltd, in relation to the subdivision of lots 22, 23 and 24 Kingsway Road, Landsdale? (2) If yes, based upon these reports, will the Department of Environment confirm that condition 19 in relation to lots 22, 23 and 24 Kingsway Road, Landsdale has been fulfilled? If so, when will notification of approval be provided to the Western Australian Planning Commission? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(2) If yes, based upon these reports, will the Department of Environment confirm that condition 19 in relation to lots 22, 23 and 24 Kingsway Road, Landsdale has been fulfilled? If so, when will notification of approval be provided to the Western Australian Planning Commission? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(1) Has the Land and Water Quality Branch of the Department of Environment received two reports, carried out by MPL Pty Ltd, in relation to the subdivision of lots 22, 23 and 24 Kingsway Road, Landsdale? (2) If yes, based upon these reports, will the Department of Environment confirm that condition 19 in relation to lots 22, 23 and 24 Kingsway Road, Landsdale has been fulfilled? If so, when will notification of approval be provided to the Western Australian Planning Commission? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(2) If yes, based upon these reports, will the Department of Environment confirm that condition 19 in relation to lots 22, 23 and 24 Kingsway Road, Landsdale has been fulfilled? If so, when will notification of approval be provided to the Western Australian Planning Commission? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
I thank the member for some notice of this question, and I provide a response on behalf of the Minister for the Environment. (1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(1) Yes; the Land and Water Quality Branch of the Department of Environment received complete copies of two environmental site assessment reports prepared by environmental consultants MPL Pty Ltd in relation to the subdivision of lots 22, 23 and 24 Kingsway Rd, Landsdale on 31 August 2005. (2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
(2) No; additional information is required from the developer and/or its consultant to fulfil condition 19 of Western Australian Planning Commission subdivision approval 125154. The Department of Environment has already advised the developer and MPL Pty Ltd by telephone that further information is required, and will provide written advice to this effect by 16 September 2005.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.