❓ Ms. Saffioti asks about the progress of the Malaga Drive and Reid Highway overpass project announced in December 2012. The government provides an update on planning, construction start, and completion dates.
AnsweredQoN 17Legislative Assembly
QuestionView source ↗
I refer to the State Government’s announcement in December 2012 to construct a $75 million overpass at the intersection of Malaga Drive and Reid Highway, and ask:
(a) has planning and design of the overpass been completed;
(b) when will construction begin; and
(c) when will construction be completed and the project finished?
(a) has planning and design of the overpass been completed;
(b) when will construction begin; and
(c) when will construction be completed and the project finished?
AnswerView source ↗
Answered
22 May 2013
Responded by
Minister for Transport
Response time
35 days
Main Roads Western Australia advises:
(a) The majority of planning is completed and approvals are in progress.
(b) Construction is planned to begin in 2014, subject to environmental approvals.
(c) 2015.
(a) The majority of planning is completed and approvals are in progress.
(b) Construction is planned to begin in 2014, subject to environmental approvals.
(c) 2015.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.