Hon George Cash inquires about the status of the power procurement agreement between Western Power and Woodside EEC for gas-fired power stations in the North West, and the options available to Western Power following its termination. The Minister's answer confirms the termination and outlines Western Power's exploration of alternative solutions.

AnsweredQoN 281Legislative Council
Asked
24 October 2001
Portfolio
Energy

QuestionView source ↗

(1) What is the current status of the power procurement agreement between Western Power and Woodside EEC for the development of gas fired power stations in the North West?
(2) Should the agreement have been terminated, what options are available to Western Power?

AnswerView source ↗

Answered
27 November 2001
Responded by
Minister for Housing and Works representing the Minister for Energy
Response time
34 days
2) The Western Power Board decided to terminate the Agreement for a number of reasons. Western Power is examining a number of options to bring new power generation facilities to the West Kimberley including replacing its aging generation sets through its own means. It will advise the Minister for Energy of its recommended solution in due course.