Hon Kim Chance inquires about the status of contracts for a third transformer at the Muchea sub-station and whether its costs are linked to the 'Royalties for Regions' program. The Minister confirms contracts have been awarded and the project is not linked to the 'Royalties for Regions' program.

AnsweredQoN 29Legislative Council
Asked
25 November 2008
Portfolio
Energy

QuestionView source ↗

(1) Have the contracts for the installation of a third transformer at the Muchea sub-station been awarded?
(2) If no to (1), when it is expected that the contracts for the installation of a third transformer at the Muchea sub-station will be awarded?
(3) Is it intended that the costs for the installation of a third transformer at the Muchea sub-station will be treated as a component of the ‘Royalties for Regions’ package?

AnswerView source ↗

Answered
16 March 2009
Responded by
Minister for Energy
Response time
111 days
The Minister for Energy has been provided with the following response
(1) Yes, with remaining contracts for the steel fabrication and civil works expected to be awarded before the end of the financial year.
(2) The remaining contracts are to be awarded by the end of the financial year
(3) No
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more