❓ A WA parliamentary question regarding audits and remedial work on Rottnest Island accommodation following a tragic death. The Minister provides updates on the emergency and independent audits, and the status of remedial work.
AnsweredQoN 1098Legislative Council
QuestionView source ↗
ROTTNEST ISLAND ACCOMMODATION — EMERGENCY AUDIT
I refer to the aftermath of the tragic death of toddler Thomas Brasier on Rottnest Island. (1) Will the minister table the emergency audit of accommodation undertaken; and, if not, why not? (2) Has the promised independent audit of accommodation on the island been completed; and, if not, when will it be completed? (3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER
I refer to the aftermath of the tragic death of toddler Thomas Brasier on Rottnest Island. (1) Will the minister table the emergency audit of accommodation undertaken; and, if not, why not? (2) Has the promised independent audit of accommodation on the island been completed; and, if not, when will it be completed? (3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER
AnswerView source ↗
I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(1) Will the minister table the emergency audit of accommodation undertaken; and, if not, why not? (2) Has the promised independent audit of accommodation on the island been completed; and, if not, when will it be completed? (3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(2) Has the promised independent audit of accommodation on the island been completed; and, if not, when will it be completed? (3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(1) Will the minister table the emergency audit of accommodation undertaken; and, if not, why not? (2) Has the promised independent audit of accommodation on the island been completed; and, if not, when will it be completed? (3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(2) Has the promised independent audit of accommodation on the island been completed; and, if not, when will it be completed? (3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(3) If yes to (2), what other units have been identified as requiring remedial structural work? (4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(4) Will the minister table the independent audit; and, if not, why not? (5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(5) Has remedial work been started on the five units initially identified as unsound? (6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(6) If the work has started, what is the name of the company undertaking the work and when is it expected to be completed? Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
Hon DONNA FARAGHER replied: I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
I thank the member for some notice of this question. (1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(1) Not applicable. The emergency safety audit of masonry columns was a physical process with reinforcement works completed within a 24-hour period. (2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(2)-(3) The fieldwork component of the independent audit is complete. A report is expected to be available to the Rottnest Island Authority on 16 November. (4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(4) Not applicable. The audit report has not yet been finalised. (5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(5) Yes. (6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
(6) The work was completed by Programmed Maintenance Services, facilities managers to the Rottnest Island Authority, on 29 October 2009.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.