Question regarding funding and completion date for public infrastructure projects in Northam, specifically the Avon Health and Emergency Services Precinct. Funding of $4,814,550 was provided in 2012, and the expected completion date is July 2014.

AnsweredQoN 2236Legislative Assembly
Asked
10 April 2014
Portfolio
Regional Development

QuestionView source ↗

I refer to “Public Infrastructure: local bus service route, health and emergency services development, central business areas development, housing development”, listed as a priority project in the Northam Regional Centre Growth Plan and ask: (a) how much funding has the project received for the financial years: (i) 2011–2012; and (ii) 2012–2013; (b) how much funding has been allocated for the project for the financial years: (i) 2013–2014; (ii) 2014–2015; and (iii) 2016–2017; and (c) what is the expected completion date for the project?

AnswerView source ↗

Answered
8 May 2014
Responded by
Minister for Regional Development
Response time
28 days
(a) (i)-(ii) On 15 August 2012, $4 814 550 was deposited into the relevant Shire account for the Avon Health and Emergency Services Precinct  project.
(c)  The anticipated project completion date is July 2014.