Hon Simon O'Brien asks about structural problems at Lynwood Senior High School, specifically roof and guttering. Hon Ljiljanna Ravlich responds, detailing repair requests, a condition report identifying necessary replacements, and a cost estimate of $350,000, noting the report has been passed to the Department of Education and Training.

AnsweredQoN 724Legislative Council
Asked
5 September 2007
Portfolio
Housing and Works

QuestionView source ↗

LYNWOOD SENIOR HIGH SCHOOL - STRUCTURAL PROBLEMS
(1) How many reports of damage or requests for corrective works to the roof, guttering and related infrastructure at Lynwood Senior High School have been lodged with the department since 1 July 2007? (2) Has the state of repair of these parts of the school’s buildings been assessed, and, if so - (a) what repairs or replacement is required; and (b) when will the works be carried out? Hon LJILJANNA RAVLICH

AnswerView source ↗

I thank the honourable member for some notice of the question. (1) The department’s records show that, to date, 12 requests have been received by its call centre to repair roof leaks at Lynwood Senior High School since 1 July 2007 and have been promptly attended to and repaired. (2) (a) Because of the frequency of callouts, a detailed condition report of the roof and gutters on all buildings at the school was immediately conducted and has been completed. The report identifies areas of roof cladding that are damaged and require replacement. In addition, the report identifies gutters and downpipes that are rusted and require replacement. The cost estimate for this work is in the order of $350 000. (b) The report and cost estimates have been provided to the Department of Education and Training.
(2) Has the state of repair of these parts of the school’s buildings been assessed, and, if so - (a) what repairs or replacement is required; and (b) when will the works be carried out? Hon LJILJANNA RAVLICH replied: I thank the honourable member for some notice of the question. (1) The department’s records show that, to date, 12 requests have been received by its call centre to repair roof leaks at Lynwood Senior High School since 1 July 2007 and have been promptly attended to and repaired. (2) (a) Because of the frequency of callouts, a detailed condition report of the roof and gutters on all buildings at the school was immediately conducted and has been completed. The report identifies areas of roof cladding that are damaged and require replacement. In addition, the report identifies gutters and downpipes that are rusted and require replacement. The cost estimate for this work is in the order of $350 000. (b) The report and cost estimates have been provided to the Department of Education and Training.
(b) when will the works be carried out?
I thank the honourable member for some notice of the question. (1) The department’s records show that, to date, 12 requests have been received by its call centre to repair roof leaks at Lynwood Senior High School since 1 July 2007 and have been promptly attended to and repaired. (2) (a) Because of the frequency of callouts, a detailed condition report of the roof and gutters on all buildings at the school was immediately conducted and has been completed. The report identifies areas of roof cladding that are damaged and require replacement. In addition, the report identifies gutters and downpipes that are rusted and require replacement. The cost estimate for this work is in the order of $350 000. (b) The report and cost estimates have been provided to the Department of Education and Training.
(1) The department’s records show that, to date, 12 requests have been received by its call centre to repair roof leaks at Lynwood Senior High School since 1 July 2007 and have been promptly attended to and repaired. (2) (a) Because of the frequency of callouts, a detailed condition report of the roof and gutters on all buildings at the school was immediately conducted and has been completed. The report identifies areas of roof cladding that are damaged and require replacement. In addition, the report identifies gutters and downpipes that are rusted and require replacement. The cost estimate for this work is in the order of $350 000. (b) The report and cost estimates have been provided to the Department of Education and Training.
(2) (a) Because of the frequency of callouts, a detailed condition report of the roof and gutters on all buildings at the school was immediately conducted and has been completed. The report identifies areas of roof cladding that are damaged and require replacement. In addition, the report identifies gutters and downpipes that are rusted and require replacement. The cost estimate for this work is in the order of $350 000. (b) The report and cost estimates have been provided to the Department of Education and Training.