❓ WA Parliamentary Question regarding the Country Pathways Grant Scheme, detailing funding allocation, responsible administration, and project commencement dates in various towns and communities in the North West of the State.
AnsweredQoN 1048Legislative Assembly
QuestionView source ↗
(b) in which towns and communities were, or will the funds, be spent; (c) who was, or will be, responsible for administering the funds; and (d) when did, or when will, the programs commence operation in each town referred to above?
(c) who was, or will be, responsible for administering the funds; and (d) when did, or when will, the programs commence operation in each town referred to above?
(d) when did, or when will, the programs commence operation in each town referred to above?
b) Broome, Derby, Carnarvon, Exmouth, Fitzroy Crossing, Halls Creek, Karratha, Kununurra, Roebourne, South Hedland, Tom Price, and the Shire of East Pilbara. c) The Country Pathways Grant Scheme is administered by the Department for Planning and Infrastructure. Prior to 2002 the former Department of Transport administered the Scheme. Project Construction is administered by Local Government which is required to match Country Pathways funding on a dollar for dollar basis. d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements. 2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
c) The Country Pathways Grant Scheme is administered by the Department for Planning and Infrastructure. Prior to 2002 the former Department of Transport administered the Scheme. Project Construction is administered by Local Government which is required to match Country Pathways funding on a dollar for dollar basis. d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements. 2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements. 2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
(c) who was, or will be, responsible for administering the funds; and (d) when did, or when will, the programs commence operation in each town referred to above?
(d) when did, or when will, the programs commence operation in each town referred to above?
b) Broome, Derby, Carnarvon, Exmouth, Fitzroy Crossing, Halls Creek, Karratha, Kununurra, Roebourne, South Hedland, Tom Price, and the Shire of East Pilbara. c) The Country Pathways Grant Scheme is administered by the Department for Planning and Infrastructure. Prior to 2002 the former Department of Transport administered the Scheme. Project Construction is administered by Local Government which is required to match Country Pathways funding on a dollar for dollar basis. d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements. 2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
c) The Country Pathways Grant Scheme is administered by the Department for Planning and Infrastructure. Prior to 2002 the former Department of Transport administered the Scheme. Project Construction is administered by Local Government which is required to match Country Pathways funding on a dollar for dollar basis. d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements. 2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements. 2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02. 3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01. 4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00 5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
5) Information not available for projects constructed in 1998/99 6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
AnswerView source ↗
Answered
3 June 2003
Responded by
Minister for Planning and Infrastructure
Response time
97 days
a) At the completion of projects in the 2002-03 funding round of the Country Pathways Grant Scheme, funds spent on the North West of the State over the past 7 years have amounted to approximately $680,000.00.
b) Broome, Derby, Carnarvon, Exmouth, Fitzroy Crossing, Halls Creek, Karratha, Kununurra, Roebourne, South Hedland, Tom Price, and the Shire of East Pilbara.
c) The Country Pathways Grant Scheme is administered by the Department for Planning and Infrastructure. Prior to 2002 the former Department of Transport administered the Scheme. Project Construction is administered by Local Government which is required to match Country Pathways funding on a dollar for dollar basis.
d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements.
2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02.
3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01.
4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00
5) Information not available for projects constructed in 1998/99
6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
b) Broome, Derby, Carnarvon, Exmouth, Fitzroy Crossing, Halls Creek, Karratha, Kununurra, Roebourne, South Hedland, Tom Price, and the Shire of East Pilbara.
c) The Country Pathways Grant Scheme is administered by the Department for Planning and Infrastructure. Prior to 2002 the former Department of Transport administered the Scheme. Project Construction is administered by Local Government which is required to match Country Pathways funding on a dollar for dollar basis.
d) 1) Projects in Broome, Halls Creek, Tom Price, Port Hedland, Roebourne Carnarvon and Exmouth and the Shire of Derby-West Kimberley, have been be funded in 2002/2003. Commencement of construction is dependent on Local Government arrangements.
2) Projects in Fitzroy Crossing, Halls Creek, South Hedland, Karratha, Kununurra, Carnarvon and Exmouth were constructed in 2001/02.
3) Projects in Broome, Derby, Halls Creek, Karratha and Carnarvon were constructed in 2000/01.
4) Projects in Broome, Derby and Halls Creek were constructed in 1999/00
5) Information not available for projects constructed in 1998/99
6) Projects in Broome, Carnarvon, Derby, Fitzroy Crossing and the Shire of East Pilbara were constructed in 1997/98.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.