A WA parliamentary question regarding the development of a new police station in Mundijong. The response indicates a business case is being prepared, but funding has not yet been allocated. Remedial work at the existing station will be undertaken as needed within budget constraints.

AnsweredQoN 1173Legislative Council
Asked
19 November 2009
Portfolio
Police

QuestionView source ↗

MUNDIJONG POLICE STATION
I refer to the election commitment to develop a new police station in the Serpentine-Jarrahdale area. (1) Do plans exist for a new police station? (2) If so, what are they and what is the time frame? (3) Have moneys been allocated in the budget for this project? (4) What remedial work, if any, will be undertaken in the meantime at Mundijong Police Station, and when will that occur? Hon PETER COLLIER

AnswerView source ↗

I thank the member for some notice of this question. (1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(1) Do plans exist for a new police station? (2) If so, what are they and what is the time frame? (3) Have moneys been allocated in the budget for this project? (4) What remedial work, if any, will be undertaken in the meantime at Mundijong Police Station, and when will that occur? Hon PETER COLLIER replied: I thank the member for some notice of this question. (1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(2) If so, what are they and what is the time frame? (3) Have moneys been allocated in the budget for this project? (4) What remedial work, if any, will be undertaken in the meantime at Mundijong Police Station, and when will that occur? Hon PETER COLLIER replied: I thank the member for some notice of this question. (1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(3) Have moneys been allocated in the budget for this project? (4) What remedial work, if any, will be undertaken in the meantime at Mundijong Police Station, and when will that occur? Hon PETER COLLIER replied: I thank the member for some notice of this question. (1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(4) What remedial work, if any, will be undertaken in the meantime at Mundijong Police Station, and when will that occur? Hon PETER COLLIER replied: I thank the member for some notice of this question. (1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
Hon PETER COLLIER replied: I thank the member for some notice of this question. (1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
I thank the member for some notice of this question. (1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(1) A business case is being prepared seeking funding for the construction of a new police station in Mundijong. (2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(2) The procurement of this project is a high priority for WA Police. However, the time frame is dependent upon the provision of government funding. (3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(3) No. (4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.
(4) Through its maintenance program, WA Police undertakes remedial work as and when identified within funding constraints.