Hon Steve Martin's question regarding Onslow Port's capacity and turnaround times in 2024-25 was unanswered, as the port is privately operated and the Department lacks the requested data.

AnsweredQoN 440Legislative Council
Asked
13 August 2025
Portfolio
Transport

QuestionView source ↗

I refer to the port of Onslow, and I ask: (a) for each berth/jetty, what was the berth capacity utilisation, expressed as a percentage, for 2024-25; (b) for each berth/jetty, what was the average turnaround time (average hours) for 2024-25; (c) what was the total capacity utilisation, expressed as a percentage, for 2024-25; and (d) what was the average turnaround time (average hours) for 2024-25?

AnswerView source ↗

Answered
18 September 2025
Responded by
Minister for Transport
Response time
10 days
(a)-(d)  The Onslow Port facility is operated by a private company who is the sole user of the facility.
As such, the Department of Transport and Major Infrastructure is not responsible for the day-to-day commercial operations or the collection of associated data.