❓ A parliamentary question regarding the status of the Bundegi boat ramp project in Exmouth, including tendering, budget, timelines, and community consultation. The response provides updates on the project's progress, budget, and community engagement.
AnsweredQoN 454Legislative Council
QuestionView source ↗
BUNDEGI BOAT RAMP - EXMOUTH
(1) Can the parliamentary secretary inform the house of the current status of the Bundegi boat ramp at Exmouth? (2) Has the contract been put out to tender; and, if so, how many companies tendered on the project and how much has been budgeted for the Bundegi boat ramp project? (3) Which company was the successful tenderer for the Bundegi boat ramp? (4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA
(1) Can the parliamentary secretary inform the house of the current status of the Bundegi boat ramp at Exmouth? (2) Has the contract been put out to tender; and, if so, how many companies tendered on the project and how much has been budgeted for the Bundegi boat ramp project? (3) Which company was the successful tenderer for the Bundegi boat ramp? (4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA
AnswerView source ↗
I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(2) Has the contract been put out to tender; and, if so, how many companies tendered on the project and how much has been budgeted for the Bundegi boat ramp project? (3) Which company was the successful tenderer for the Bundegi boat ramp? (4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(3) Which company was the successful tenderer for the Bundegi boat ramp? (4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(2) Has the contract been put out to tender; and, if so, how many companies tendered on the project and how much has been budgeted for the Bundegi boat ramp project? (3) Which company was the successful tenderer for the Bundegi boat ramp? (4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(3) Which company was the successful tenderer for the Bundegi boat ramp? (4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(4) What is the time frame for calling tenders on the Bundegi boat ramp project, and when is it expected that work will commence? (5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(5) Have any financial, contractual or environmental issues impeded the progress of the Bundegi boat ramp? (6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(6) Has the Department for Planning and Infrastructure kept the Exmouth community advised about the status of this project? Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
Hon ADELE FARINA replied: I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
I thank the member for some notice of this question and for his interest in this matter. (1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(1) The ramp at Bundegi has been designed and tenders are in the final stage of assessment. (2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(2) Tenders were called for construction and four bids were received. The Exmouth ramps have an overall state-funded budget of $1.52 million. (3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(3) A contract is proposed to be awarded to the successful tenderer, subject to financial checks being satisfactory. (4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(4) Works are currently expected to commence on the site in November this year. Works could have commenced earlier but there is at least a two-month lead time on the precast concrete components. (5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(5) No. The project has received environmental approval from the state agencies and the acceptance of the adjoining commonwealth landowner. Financial checks are currently being undertaken on the preferred tenderer. (6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
(6) The project has been coordinated by both the Department for Planning and Infrastructure and the Shire of Exmouth. The shire has had a community reference group in place to guide concept planning and consultation for the project.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.