Hon Ken Travers asks about the planning, timeline, and budget for the Perth to Fremantle Railway Line Principal Shared Path (PSP) from Shenton Park to Loch Street. The Minister provides details on design completion, commencement and completion dates, cost estimation, and budget allocation.

AnsweredQoN 1832Legislative Council
Asked
21 October 2014
Portfolio
Transport

QuestionView source ↗

I refer to the Western Australia Bicycle Network Plan and ask, for the priority link Perth to Fremantle Railway Line from Shenton Park to Loch Street: (a) what planning work has been done on this link; (b) what are the details of the works required; (c) when does the Minister expect work to commence; (d) when does the Minister expect works to be completed; (e) what is the estimated cost of this project; and (f) how much is currently allocated in the 2014-15 State Budget and in each year of the forward estimates?

AnswerView source ↗

Answered
3 December 2014
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
43 days
(a-b) It is proposed to install a Principal Shared Path. Detailed design is nearing completion.
(c-d) Works will commence in early 2015 and be completed by the end of 2015.
(e) The cost estimate will be finalised after the design has been completed.
(f) 2014-15 - $2.59 million
2015-16 - $3.11 million