A WA parliamentary question seeks a breakdown of construction costs for the South West Metropolitan Railway project and details of any works in Packages A and F not funded by the MetroRail budget. The answer provides cost estimates for each package and confirms that all committed works in Packages A, E, and F are funded within the project budget, with optional works under consideration.

AnsweredQoN 1608Legislative Assembly
Asked
3 June 2003
Portfolio
Planning and Infrastructure

QuestionView source ↗

(b) stations at Thomsons Lake and Thomas Road (Package B); (c) stations at Rockingham, Waikiki and Mandurah (Package C); (d) stations at South Street, Leach Highway and Canning Bridge (Package D); (e) Narrows Bridge to Glen Iris (Package E); (f) Narrows Bridge to Perth Yard (Package F); and (g) Train Control Systems (Package G)?
(c) stations at Rockingham, Waikiki and Mandurah (Package C); (d) stations at South Street, Leach Highway and Canning Bridge (Package D); (e) Narrows Bridge to Glen Iris (Package E); (f) Narrows Bridge to Perth Yard (Package F); and (g) Train Control Systems (Package G)?
(d) stations at South Street, Leach Highway and Canning Bridge (Package D); (e) Narrows Bridge to Glen Iris (Package E); (f) Narrows Bridge to Perth Yard (Package F); and (g) Train Control Systems (Package G)?
(e) Narrows Bridge to Glen Iris (Package E); (f) Narrows Bridge to Perth Yard (Package F); and (g) Train Control Systems (Package G)?
(f) Narrows Bridge to Perth Yard (Package F); and (g) Train Control Systems (Package G)?
(g) Train Control Systems (Package G)?
(b) details of any works in Package A not funded by the MetroRail budget; and (c) details of any works in Package F not funded by the MetroRail budget?
(c) details of any works in Package F not funded by the MetroRail budget?
(a) Package A: Civil, structures and drainage works between Glen Iris and Mandurah and the railway infrastructure works from the Narrows Bridge to Mandurah: $280 million. (b) Package B: stations at Thomsons Lake, Thomas Road and Leda: $23 million. (c) Package C: Stations at Rockingham, Waikiki and Mandurah: $ 32 million. (d) Package D: Stations at Canning Bridge, Leach Highway and South Street: $34 million. (e) Package E: MRWA bridge and freeway works between the Narrows Bridge and Glen Iris: $100 million. (f) Package F: City Rail works between the Narrows Bridge and Perth Yard: $200 million. (g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million). (2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.
(b) Package B: stations at Thomsons Lake, Thomas Road and Leda: $23 million. (c) Package C: Stations at Rockingham, Waikiki and Mandurah: $ 32 million. (d) Package D: Stations at Canning Bridge, Leach Highway and South Street: $34 million. (e) Package E: MRWA bridge and freeway works between the Narrows Bridge and Glen Iris: $100 million. (f) Package F: City Rail works between the Narrows Bridge and Perth Yard: $200 million. (g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million). (2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.
(c) Package C: Stations at Rockingham, Waikiki and Mandurah: $ 32 million. (d) Package D: Stations at Canning Bridge, Leach Highway and South Street: $34 million. (e) Package E: MRWA bridge and freeway works between the Narrows Bridge and Glen Iris: $100 million. (f) Package F: City Rail works between the Narrows Bridge and Perth Yard: $200 million. (g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million). (2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.
(d) Package D: Stations at Canning Bridge, Leach Highway and South Street: $34 million. (e) Package E: MRWA bridge and freeway works between the Narrows Bridge and Glen Iris: $100 million. (f) Package F: City Rail works between the Narrows Bridge and Perth Yard: $200 million. (g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million). (2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.
(e) Package E: MRWA bridge and freeway works between the Narrows Bridge and Glen Iris: $100 million. (f) Package F: City Rail works between the Narrows Bridge and Perth Yard: $200 million. (g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million). (2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.
(f) Package F: City Rail works between the Narrows Bridge and Perth Yard: $200 million. (g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million). (2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.
(g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million). (2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.
(2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.

AnswerView source ↗

Answered
27 August 2003
Responded by
Minister for Planning and Infrastructure
Response time
85 days
(1) The breakdown of construction cost estimates for the major work packages for the South West Metropolitan Railway as outlined in the Supplementary Master Plan are:
(a) Package A: Civil, structures and drainage works between Glen Iris and Mandurah and the railway infrastructure works from the Narrows Bridge to Mandurah: $280 million.
(b) Package B: stations at Thomsons Lake, Thomas Road and Leda: $23 million.
(c) Package C: Stations at Rockingham, Waikiki and Mandurah: $ 32 million.
(d) Package D: Stations at Canning Bridge, Leach Highway and South Street: $34 million.
(e) Package E: MRWA bridge and freeway works between the Narrows Bridge and Glen Iris: $100 million.
(f) Package F: City Rail works between the Narrows Bridge and Perth Yard: $200 million.
(g) Package G: Train Control and Customer Information System: $5.8 million (Please note that this amount is included in the contract for the system wide train control and customer information system contract valued at $10.6 million).
(2) (a) - (c) The tenders for Packages A, E and F include the scope of works described in the Supplementary Master Plan. All the works committed to be undertaken in Packages A, E and F are funded within the New MetroRail Project budget. The tenders for these packages also provide for prices to be obtained for a number of optional works to determine if these works can be delivered within the project budget. If favourable tender prices are received a decision will be made on whether the opportunity will be taken to take up any optional works.