❓ Question regarding the timeline, funding, and cost of a westbound climbing lane construction project near Boddington. The Minister provides a timeline for design commencement, notes funding is subject to budgetary processes, and estimates the cost.
AnsweredQoN 5694Legislative Assembly
QuestionView source ↗
(1) Can the Minister please advise when plans for constructing a westbound climbing lane approximately 20km from Boddington (SLK 55) will be finalised? (2) When will funding be allocated for this upgrade? (3) How much is the upgrade anticipated to cost?
AnswerView source ↗
Answered
26 November 2019
Responded by
Minister for Transport; Planning
Response time
8 days
(1) Main Roads will begin design for a westbound climbing lane on Pinjarra Williams Road in the upcoming financial year.
(2) Funding is subject to standard budgetary processes.
(3) The estimated cost is $3 million
(2) Funding is subject to standard budgetary processes.
(3) The estimated cost is $3 million
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.