Question regarding funding and completion date for the Southern leg of the Margaret River perimeter road, a priority project in the SuperTown Townsite Growth Plan. The answer provides funding details and an expected completion date.

AnsweredQoN 2229Legislative Assembly
Asked
10 April 2014
Portfolio
Regional Development

QuestionView source ↗

I refer to the Southern leg of the perimetre road, listed as a priority project in the Margaret River SuperTown Townsite Growth Plan and ask: (a) how much funding has the project received for the financial years: (i) 2011–2012; and (ii) 2012–2013; (b) how much funding has been allocated for the project for the financial years: (i) 2013–2014; (ii) 2014–2015; and (iii) 2016–2017; and (c) what is the expected completion date for the project?

AnswerView source ↗

Answered
8 May 2014
Responded by
Minister for Regional Development
Response time
28 days
(a) (i)-(ii) On 29 July 2012, $1 940 000 was deposited into the relevant Shire  account for the Margaret River Perimeter Road and Town Centre  Improvements project, of which $1 000 000 is related to the Margaret River Perimeter Road project.
(c) The project completion date, as stated in the financial assistance  agreement, is December 2014.