Hon Giz Watson asks about the timeline and expenditure breakdown for the $40 million upgrade to Kalgoorlie Regional Hospital. The Minister provides an estimated completion date of June 2012 and a detailed cash flow projection, while noting potential variations due to construction demands.

AnsweredQoN 5727Legislative Council
Asked
6 December 2007
Portfolio
Health

QuestionView source ↗

(1) Will the Minister give an estimated end-date for the proposed $40 million upgrade to the hospital?
(2) Will the Minister provide a program of staged expenditure for the hospital upgrade, including approximate expenditures for each stage?
(3) If no to (2), why not?
(4) Is it correct that only $2.8 million will be spent in the 2008 - 2009 year?
(5) If yes to (1), what will this amount be specifically spent on at the Kalgoorlie Regional Hospital?
(6) Can the Minister state what amount of money and the relevant ‘subsequent years’ the remaining $37.2 million dollars will be spent at the Kalgoorlie Regional Hospital?
(7) If no to (5), why not?

AnswerView source ↗

Answered
18 February 2008
Responded by
Minister for Child Protection representing the Minister for Health
Response time
74 days
(1) - (7)
The current estimated end-date for the proposed upgrade of Kalgoorlie Regional Hospital is the financial year ending June 2012. However, due to the volume of construction work occurring in Western Australia, there may be some variation to this estimated end-date, which cannot be seen at this point in time.
The estimated cash flow for this project is as follows and is predicated on a completion date of June 2012:
· 2007-2008 - $ 0.30 million;
· 2008-2009 - $ 2.80 million;
· 2009-2010 - $10.72 million;
· 2010-2011 - $ 17.43 million;
· 2011-2012 - $ 8.68 million; and
· 2012-2013 - $ 0.07 million.
The project is subject to a comprehensive business case submission to the Department of Treasury and Finance. Detailed costings for each stage will form part of the documentation work within the final business case, which is yet to be approved. The preferred option in the business case includes building a new clinical block incorporating Emergency Department, High Dependency Unit, Medical Imaging and Medical Records, and enhancing the Day Surgery Ward, Theatres and sterilisation areas. In addition, a new palliative care unit will be constructed and the old Emergency Department will be partially refurbished for use by Allied Health.
A Forward Works Package of approximately $2.8 million is proposed in 2008/09 and will include urgent work to address drainage issues near the Emergency Department, construction of a new lift between the Emergency Department and Medical Imaging; and replacement of the emergency generator.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more