A WA parliamentary question regarding a 'works agreement' repayment owed to Port Kennedy Resorts Pty Ltd, which is under administration. The Minister confirms the agreement exists but payment is not yet due and will be made to the administrators when due.

AnsweredQoN 610Legislative Assembly
Asked
4 December 2002
Portfolio
Government Enterprises

QuestionView source ↗

(b) is the Minister aware of the provisions of the Corporations (Administrative Actions) Act 2001 , relating to Administration, Receivership and Liquidation of Proprietary Limited companies; (c) as this ‘works agreement’ repayment is an asset of Port Kennedy Resorts Pty Ltd., has the agreement been paid out to the Administrators of Port Kennedy Resorts; (d) if not, why not; (e) will the Minister now direct that the ‘works agreement’ repayment be paid to the Administrator of Port Kennedy Resorts Pty Ltd; (f) if not, why not; and (g) has the Minister sought Crown Law advice on the status of the ‘works agreement’ repayment?
(c) as this ‘works agreement’ repayment is an asset of Port Kennedy Resorts Pty Ltd., has the agreement been paid out to the Administrators of Port Kennedy Resorts; (d) if not, why not; (e) will the Minister now direct that the ‘works agreement’ repayment be paid to the Administrator of Port Kennedy Resorts Pty Ltd; (f) if not, why not; and (g) has the Minister sought Crown Law advice on the status of the ‘works agreement’ repayment?
(d) if not, why not; (e) will the Minister now direct that the ‘works agreement’ repayment be paid to the Administrator of Port Kennedy Resorts Pty Ltd; (f) if not, why not; and (g) has the Minister sought Crown Law advice on the status of the ‘works agreement’ repayment?
(e) will the Minister now direct that the ‘works agreement’ repayment be paid to the Administrator of Port Kennedy Resorts Pty Ltd; (f) if not, why not; and (g) has the Minister sought Crown Law advice on the status of the ‘works agreement’ repayment?
(f) if not, why not; and (g) has the Minister sought Crown Law advice on the status of the ‘works agreement’ repayment?
(g) has the Minister sought Crown Law advice on the status of the ‘works agreement’ repayment?
(b) Yes. (c) No. (d) Under the conditions of the Customer Constructed Works Agreement binding the parties involved, payment which is subject to claim, is not due until 10 June 2003. (e) No, payment will be made to the Administrators of Port Kennedy Resorts Pty Ltd when it becomes due under the conditions of the Customer Constructed Works Agreement. (f) Not applicable. (g) No.
(c) No. (d) Under the conditions of the Customer Constructed Works Agreement binding the parties involved, payment which is subject to claim, is not due until 10 June 2003. (e) No, payment will be made to the Administrators of Port Kennedy Resorts Pty Ltd when it becomes due under the conditions of the Customer Constructed Works Agreement. (f) Not applicable. (g) No.
(d) Under the conditions of the Customer Constructed Works Agreement binding the parties involved, payment which is subject to claim, is not due until 10 June 2003. (e) No, payment will be made to the Administrators of Port Kennedy Resorts Pty Ltd when it becomes due under the conditions of the Customer Constructed Works Agreement. (f) Not applicable. (g) No.
(e) No, payment will be made to the Administrators of Port Kennedy Resorts Pty Ltd when it becomes due under the conditions of the Customer Constructed Works Agreement. (f) Not applicable. (g) No.
(f) Not applicable. (g) No.
(g) No.

AnswerView source ↗

Answered
25 February 2003
Responded by
Minister representing the Minister for Government Enterprises
Response time
83 days
(a) The Water Corporation advises me that it is committed to a Customer Constructed Works Agreement, signed on 4 July 2000, with an outstanding contract liability of $503 000.
(b) Yes.
(c) No.
(d) Under the conditions of the Customer Constructed Works Agreement binding the parties involved, payment which is subject to claim, is not due until 10 June 2003.
(e) No, payment will be made to the Administrators of Port Kennedy Resorts Pty Ltd when it becomes due under the conditions of the Customer Constructed Works Agreement.
(f) Not applicable.
(g) No.