❓ Question regarding the construction progress, completion date, and availability of beds for the 344-bed addition at Casuarina Prison. The answer provides a status update, planned completion dates, and indicates bed availability will be determined later.
AnsweredQoN 5702Legislative Assembly
QuestionView source ↗
I refer to the 344-bed addition to be completed at Casuarina Prison, and I ask: (a) At what stage of construction is the upgrade currently; (b) When will works be complete; and (c) When will the beds be available for use?
AnswerView source ↗
Answered
26 November 2019
Responded by
Minister for Emergency Services; Corrective Services
Response time
7 days
(a) The project is currently at Project Definition Stage (to be considered by Government in early 2020).
(b) Dates will be confirmed following approval of the Project Delivery Plan, delivery is planned in two stages targeting late 2022 and late 2023.
(c) At a date to be determined closer to completion of the project.
(b) Dates will be confirmed following approval of the Project Delivery Plan, delivery is planned in two stages targeting late 2022 and late 2023.
(c) At a date to be determined closer to completion of the project.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.