A parliamentary question seeks details on funding and completion date for the Katanning Town Centre Revitalisation project. The answer provides funding details for 2012 and the expected completion date.

AnsweredQoN 2215Legislative Assembly
Asked
10 April 2014
Portfolio
Regional Development

QuestionView source ↗

I refer to the Town Centre Commercial and Streetscape Revitalisation, listed as a priority project in the Katanning SuperTown Growth and Implementation Plan and ask: (a) how much funding has the project received for the financial years: (i) 2011–2012; and (ii) 2012–2013; (b) how much funding has been allocated for the project for the financial years: (i) 2013–2014; (ii) 2014–2015; and (iii) 2016–2017; and (c) what is the expected completion date for the project?

AnswerView source ↗

Answered
8 May 2014
Responded by
Minister for Regional Development
Response time
28 days
(a) (i)-(ii) On 29 June 2012, $8 715 000 was deposited into the relevant Shire account for the Town Centre Commercial and Streetscape Revitalisation Project in Katanning.
(c) The project completion date, as stated in the Financial Assistance Agreement, is 30 December 2014.