❓ Hon Steve Martin asks the Minister for Transport about the estimated expenditure for various projects under the High Capacity Signalling Program of Works up to 30 June 2025. The Minister provides the requested financial figures for each project.
AnsweredQoN 543Legislative Council
QuestionView source ↗
I refer to the individual component parts of the High Capacity Signalling Program of Works, and Estimates pre-hearing questions requesting the current estimated expenditure to 30 June 2025 for each of the projects, which was not provided, and I ask: (a) what is the total estimated expenditure to 30 June 2025 for each of the following projects: (i) High Capacity Signalling - Delivery; (ii) High Capacity Signalling - Owners cost; (iii) Nowergup Railcar Modification Shed; and (iv) Public Transport Operations Control Centre?
AnswerView source ↗
Answered
14 October 2025
Responded by
Parliamentary Secretary to the Minister for Transport
Response time
6 days
(a) (i) $74,612, 000
(ii) $51,847,000
(iii) $31,619,000
(iv) $88,730,000
(ii) $51,847,000
(iii) $31,619,000
(iv) $88,730,000
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.