❓ A parliamentary question regarding the commencement of roadworks on Wanneroo Road, specifically concerning the impact of the 2008 state budget on the project's timeline and the status of pre-construction activities. The answer indicates the project's timing is budget-dependent and design work is progressing.
AnsweredQoN 408Legislative Council
QuestionView source ↗
WANNEROO ROAD, PINJAR ROAD-JOONDALUP DRIVE — ROAD SAFETY
I refer to traffic safety concerns on the section of Wanneroo Road between Pinjar Road and Joondalup Drive and the minister’s previous indication of advanced planning by Main Roads WA. (1) Is it still intended that Main Roads will start work on this section of road in October 2008? (2) If so, what design and other preconstruction activities are currently being undertaken? (3) If no to (1), why not? Hon SALLY TALBOT
I refer to traffic safety concerns on the section of Wanneroo Road between Pinjar Road and Joondalup Drive and the minister’s previous indication of advanced planning by Main Roads WA. (1) Is it still intended that Main Roads will start work on this section of road in October 2008? (2) If so, what design and other preconstruction activities are currently being undertaken? (3) If no to (1), why not? Hon SALLY TALBOT
AnswerView source ↗
I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(1) Is it still intended that Main Roads will start work on this section of road in October 2008? (2) If so, what design and other preconstruction activities are currently being undertaken? (3) If no to (1), why not? Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(2) If so, what design and other preconstruction activities are currently being undertaken? (3) If no to (1), why not? Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(3) If no to (1), why not? Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(3) Not applicable.
(1) Is it still intended that Main Roads will start work on this section of road in October 2008? (2) If so, what design and other preconstruction activities are currently being undertaken? (3) If no to (1), why not? Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(2) If so, what design and other preconstruction activities are currently being undertaken? (3) If no to (1), why not? Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(3) If no to (1), why not? Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
Hon SALLY TALBOT replied: I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
I thank Hon Ray Halligan for some notice of the question, to which I provide a response on behalf of the parliamentary secretary to the Minister for Planning and Infrastructure. The minister has responded in the following terms — (1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(1) Timing is subject to the outcome of the 2008 state budget. (2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(2) The detailed design is advanced, along with land acquisition and identification of the services to be modified. (3) Not applicable.
(3) Not applicable.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.