Hon Ray Halligan asked the Minister for Planning and Infrastructure about expenditure on upgrades to various rail lines since February 10, 2001. The Minister provided figures for the Armadale, Fremantle, Midland, and Northern Suburbs lines, including New MetroRail expenditure.

AnsweredQoN 2109Legislative Council
Asked
22 June 2004
Portfolio
Planning and Infrastructure

QuestionView source ↗

Will the Minister please advise -
(1) The total expenditure on upgrades to the Armadale rail line since February 10 2001?
(2) The total expenditure on upgrades to the Fremantle rail line since February 10 2001?
(3) The total expenditure on upgrades to the Midland rail line since February 10 2001?
(4) The total expenditure on upgrades to the northern suburbs rail line since February 10 2001?

AnswerView source ↗

Answered
19 August 2004
Responded by
Parliamentary Secretary representing the Minister for Planning and Infrastructure
Response time
58 days
(1) The total Public Transport Authority expenditure for upgrade works to the Armadale Railway is $20.86 million, of which $9.9 million is New MetroRail (NMR) expenditure for upgrade works on the Armadale line as part of the Thornlie component of the project. (2) The total Public Transport Authority expenditure for upgrade works to the Fremantle rail line is $19.84 million. (3) The total Public Transport Authority expenditure for upgrade works to the Midland rail line is $23.42 million. (4) The total Public Transport Authority expenditure for upgrade works to the Northern Suburbs Railway is $8.9 million, of which New MetroRail (NMR) expenditure is $2.6 million.
(2) The total Public Transport Authority expenditure for upgrade works to the Fremantle rail line is $19.84 million. (3) The total Public Transport Authority expenditure for upgrade works to the Midland rail line is $23.42 million. (4) The total Public Transport Authority expenditure for upgrade works to the Northern Suburbs Railway is $8.9 million, of which New MetroRail (NMR) expenditure is $2.6 million.
(3) The total Public Transport Authority expenditure for upgrade works to the Midland rail line is $23.42 million. (4) The total Public Transport Authority expenditure for upgrade works to the Northern Suburbs Railway is $8.9 million, of which New MetroRail (NMR) expenditure is $2.6 million.
(4) The total Public Transport Authority expenditure for upgrade works to the Northern Suburbs Railway is $8.9 million, of which New MetroRail (NMR) expenditure is $2.6 million.

Explore WA Government Data