❓ Hon Ray Halligan asks about the estimated construction costs and market value of sites for two planned public housing projects in Perth. Hon Kate Doust provides the estimated construction costs and the acquisition costs of the sites.
AnsweredQoN 301Legislative Council
QuestionView source ↗
I refer the minister to his announcement that the government plans to build two public housing projects in Perth. (1) What is the estimated construction cost of each of the two projects? (2) What is the estimated market value of each of the selected sites? Hon KATE DOUST
AnswerView source ↗
I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(1) What is the estimated construction cost of each of the two projects? (2) What is the estimated market value of each of the selected sites? Hon KATE DOUST replied: I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(2) What is the estimated market value of each of the selected sites? Hon KATE DOUST replied: I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
Hon KATE DOUST replied: I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(1) What is the estimated construction cost of each of the two projects? (2) What is the estimated market value of each of the selected sites? Hon KATE DOUST replied: I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(2) What is the estimated market value of each of the selected sites? Hon KATE DOUST replied: I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
Hon KATE DOUST replied: I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
I thank the member for some notice of this question. I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
I am advised - (1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(1) The estimated construction cost of the projects is $15 million and $20 million. (2) The sites were acquired at a cost of $2.05 million and $2.2 million.
(2) The sites were acquired at a cost of $2.05 million and $2.2 million.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.