This parliamentary question concerns the progress and potential delays in the construction of the Vasse Middle School, including issues related to land development and environmental contamination. The school will not open in February 2007 as planned due to developer delays and potential pesticide contamination.

AnsweredQoN 1837Legislative Council
Asked
17 May 2005
Portfolio
Education and Training

QuestionView source ↗

(1) What are the current plans for the proposed Vasse Middle School?
(2) Will the school open in February 2007 as previously indicated?
(3) If not, why not?
(4) Are there any environmental concerns linked to building the school on former agricultural land?
(5) If yes to (4), what are these concerns and what steps are being taken to address them?

AnswerView source ↗

Answered
22 June 2005
Responded by
Minister for Education and Training
Response time
36 days
(1) Architects, Hassell Pty Ltd were appointed in November 2004, and have completed the master plan for the site and are well advanced with schematic design. (2) No (3) There are subdivisional requirements which the Developer has yet to meet, therefore it is unlikely that the site will be available until early 2006 and the project tender is not expected to go out until March 2006. The developer has been unable to confirm that services (the sewer in particular) will be available to the site by 2007. (4) Yes (5) Early indications of residual pesticide contamination on the site are being investigated but it is not expected to be a material issue.
(2) No (3) There are subdivisional requirements which the Developer has yet to meet, therefore it is unlikely that the site will be available until early 2006 and the project tender is not expected to go out until March 2006. The developer has been unable to confirm that services (the sewer in particular) will be available to the site by 2007. (4) Yes (5) Early indications of residual pesticide contamination on the site are being investigated but it is not expected to be a material issue.
(3) There are subdivisional requirements which the Developer has yet to meet, therefore it is unlikely that the site will be available until early 2006 and the project tender is not expected to go out until March 2006. The developer has been unable to confirm that services (the sewer in particular) will be available to the site by 2007. (4) Yes (5) Early indications of residual pesticide contamination on the site are being investigated but it is not expected to be a material issue.
(4) Yes (5) Early indications of residual pesticide contamination on the site are being investigated but it is not expected to be a material issue.
(5) Early indications of residual pesticide contamination on the site are being investigated but it is not expected to be a material issue.