Mr. Bowler inquires about the development timelines for water purification plants in Leonora and Laverton. The Minister provides specific completion dates for both projects.

AnsweredQoN 1851Legislative Assembly
Asked
28 August 2003
Portfolio
Government Enterprises

QuestionView source ↗

Will the Minister advise on the timetables and progress in the development of water purification plants at Leonora and Laverton?

AnswerView source ↗

Answered
9 September 2003
Responded by
Minister representing the Minister for Government Enterprises
Response time
12 days
Construction of the Leonora Water Treatment Plant is scheduled to commence this month, with completion by January 2004. Completion of the Laverton Water Treatment Plant is scheduled for June 2004.
Completion of the Laverton Water Treatment Plant is scheduled for June 2004.