A parliamentary question seeks details regarding the tender awarded to Delta Group for the demolition of the Western Australian State Museum, including cost, competing bids, and completion date. The answer provides specific figures and dates, with a caveat regarding potential variations.

AnsweredQoN 4794Legislative Assembly
Asked
15 March 2011
Portfolio
Culture and the Arts

QuestionView source ↗

In relation to the tender awarded to Delta Group for the demolition of the Western Australian State Museum, I ask:
(a) what is the total cost of the tender;
(b) how many other tenders were received and what were their submitted costs; and
(c) what is the agreed completion date for the demolition and final payment of tender payments?

AnswerView source ↗

Answered
5 April 2011
Responded by
Minister for Culture and the Arts
Response time
21 days
(a) $2,911,700 GST inclusive for the Francis Street Building demolition at the WA Museum (Perth) site.
(b) Three. Submitted costs were $2,939,200, $4,890,600 and $7,480,000 all GST inclusive.
(c) The contracted date for the completion of the demolition phase is 30 September 2011, however this date may vary for a range of contractual circumstances. Final payment will be made following the expiry of the defects liability period (twelve months after practical completion). There will also be additional costs relating to the preparatory and remediation works for the site.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more