Question regarding the status of mediation between Main Roads and Brierty concerning a contractual dispute over rock encountered during the Great Eastern Highway project. The answer refers to a previous question.

AnsweredQoN 5295Legislative Assembly
Asked
24 March 2016
Portfolio
Transport

QuestionView source ↗

I refer to Main Roads Tender MRWA008913 (Great Eastern Highway) and ask: (a) has mediation between Main Roads and Brierty commenced concerning the
contractual dispute relating to the amount of rock encountered in cuttings; (b) if yes, on what date did mediation commence; (c) if no, on what date will mediation commence; (d) if mediation had commenced and concluded, what was the outcome of the
mediation; and (e) what is the name of the independent arbitrator?

AnswerView source ↗

Answered
10 May 2016
Responded by
Minister for Transport
Response time
47 days
Please refer to Legislative Assembly Question on Notice 5147.