Hon Dr Steve Thomas questions the Minister for Energy and Decarbonisation regarding delays and potential inadequacies in the South West Interconnected System's whole-of-system plan. The Minister denies a draft plan was completed on time.

AnsweredQoN 1255Legislative Council
Asked
9 December 2025
Portfolio
Energy and Decarbonisation

QuestionView source ↗

South West Interconnected System—Whole-of-system
plan
1255. Hon Dr Steve Thomas to the Leader of the House
representing the Minister for Energy and Decarbonisation:
I refer to the even
further delayed whole-of-system plan for the South West Interconnected System—
The President: Order, member! Sorry, your microphone
flicked off. You are now right to go.
Hon Dr Steve Thomas: Was it a conspiracy to silence
me, President?
The President: Honourable member, though some might
wish it, it is not the case.
Hon Dr Steve Thomas: I will start again, President.
I refer to the even
further delayed whole-of-system plan for the South West Interconnected System,
which will in theory show how the government will keep the lights on over the
next five years, including at peak demand over summer, and which was due by the
end of September 2025 but will now not be delivered until mid-2027, when the
so-called transition will be already half done.
(1) Is it true that Energy Policy WA in the Department
of Energy and Economic Diversification had completed a draft whole-of-system
plan on time for release by 30 September 2025?
(2) If yes to (1), was the draft whole-of-system
plan dropped because, in review, the government worked out that it was a
failure that could not deliver the proposed transition?
(3) Will the minister table a copy of the
inadequate draft whole-of-system plan or is it too embarrassing?
(4) How can the community have faith that the
government's next attempt at a whole-of-system transmission plan will be any
better?

AnswerView source ↗

I thank the
honourable member for some notice of the question. The following response has
been provided to me by the Minister for Energy and Decarbonisation.
(1) No.
(2)–(4) Not applicable.