Question regarding the status, cost, and delays of the investigation into the Preston River realignment for Bunbury Port expansion. The investigation is incomplete due to delayed stakeholder responses, with a current cost of $2.88M and an expected total cost of $3.3M.

AnsweredQoN 3472Legislative Council
Asked
20 October 2015
Portfolio
Transport

QuestionView source ↗

I refer to the investigation of the realignment of the Preston River to facilitate future Bunbury Port expansion, and I ask: (a) has the investigation been completed; (b) if yes to (a), has the report been released and, if not, will the Minister table the report; (c) if no to (a), when will the investigation be completed and what is causing the project to be delayed; (d) what has been the cost of the investigation to date; and (e) what is the expected total cost of the investigation?

AnswerView source ↗

Answered
1 December 2015
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
42 days
(a) No.
(b) Not applicable
(c) Investigation is due for completion in 2016. Delays have been caused by late responses from various Stakeholders.
(d) $2 877 337.31.
(e) $3 300 000.00.