A WA parliamentary question addresses the steps, progress, and community consultation regarding local area education planning in the Bunbury education district, specifically concerning promised upgrades to Newton Moore Senior High School.

AnsweredQoN 227Legislative Council
Asked
8 April 2004
Portfolio
Education and Training

QuestionView source ↗

With respect to the local area education planning in the Bunbury education district, I ask - (1) What are the steps involved? (2) What is the current state of progress? (3) When will the community be consulted? (4) Why has no information been provided to date? (5) When will action be taken to upgrade the teaching areas at the Newton Moore Senior High School as promised in the last LAEP process in 2000? Hon LJILJANNA RAVLICH

AnswerView source ↗

I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(1) What are the steps involved? (2) What is the current state of progress? (3) When will the community be consulted? (4) Why has no information been provided to date? (5) When will action be taken to upgrade the teaching areas at the Newton Moore Senior High School as promised in the last LAEP process in 2000? Hon LJILJANNA RAVLICH replied: I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(2) What is the current state of progress? (3) When will the community be consulted? (4) Why has no information been provided to date? (5) When will action be taken to upgrade the teaching areas at the Newton Moore Senior High School as promised in the last LAEP process in 2000? Hon LJILJANNA RAVLICH replied: I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(3) When will the community be consulted? (4) Why has no information been provided to date? (5) When will action be taken to upgrade the teaching areas at the Newton Moore Senior High School as promised in the last LAEP process in 2000? Hon LJILJANNA RAVLICH replied: I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(4) Why has no information been provided to date? (5) When will action be taken to upgrade the teaching areas at the Newton Moore Senior High School as promised in the last LAEP process in 2000? Hon LJILJANNA RAVLICH replied: I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(5) When will action be taken to upgrade the teaching areas at the Newton Moore Senior High School as promised in the last LAEP process in 2000? Hon LJILJANNA RAVLICH replied: I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
Hon LJILJANNA RAVLICH replied: I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
I provide this response on behalf of the parliamentary secretary representing the Minister for Education and Training. (1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(1) Phase 1 - district directors monitor schools to identify clusters of schools as appropriate for the LAEP process. Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
Phase 2 - a drafting committee is established. Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
Phase 3 - a draft plan is developed. Phase 4 - a draft plan is submitted to the department’s corporate executive for consideration. Phase 5 - a consultation process occurs. Phase 6 - the director general considers the draft plan and consultative report. Phase 7 - the minister makes a determination on the plan. Phase 8 - the plan is implemented. Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
Phase 7 - the minister makes a determination on the plan.
Phase 9 - the district director monitors the outcome. (2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(2) Phase 4. (3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(3) Phase 5. (4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(4) The process has not reached phase 5. (5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.
(5) No promise was made in the last process. Since 2000, Newton Moore Senior High School has received $1 million for an admission and design and technology upgrade, and $150 000 for a toilet upgrade. Any further development is likely to be dependent on the outcome of the current process.