Alanna Clohesy asks about the cost, timeframe, and budget allocation for replacing the Third and Seventh Avenue railway bridges on the Midland line. The Parliamentary Secretary provides specific cost and timeline details, referencing the budget paper.

AnsweredQoN 924Legislative Council
Asked
3 December 2013
Portfolio
Transport

QuestionView source ↗

MIDLAND
RAILWAY LINE — THIRD AND SEVENTH AVENUE BRIDGES
924. Hon ALANNA CLOHESY to the
parliamentary secretary representing the Minister for Transport:
I refer to the government's plans to replace the
Third and Seventh Avenue timber railway bridges on the Midland line.
(1) What is the expected cost for the replacement of each
bridge?
(2) What is the current timeframe to complete the replacement
of both bridges?
(3) Where is the funding for these replacements reflected in
the current 2013–14 state budget?

AnswerView source ↗

I thank the honourable member for some notice of this
question.
(1) It is expected that they will cost $11.4 million and
$10.5 million respectively.
(2) It is mid-2016 and mid-2015.
(3) It is on page 393 of budget paper No 2.