Mr. Catania inquires about the plans and timelines for remedial works at Tom Price Primary School following a fire, aiming to ensure minimal disruption for staff and students in 2020. The answer outlines a two-stage remediation process.

AnsweredQoN 5850Legislative Assembly
Asked
10 December 2019
Portfolio
Education and Training

QuestionView source ↗

I refer to the recent fire which severely damaged the Tom Price Primary School leaving staff and students without rooms, and facilities, and I ask: (a) What are the plans and time frames for the
completion of remedial works to ensure that staff and students are not
disadvantaged by lack of facilities when school commences in 2020 and to remove
any dysfunction?

AnswerView source ↗

Answered
11 February 2020
Responded by
Minister representing the Minister for Education and Training
Response time
1 days
(a) The fire-affected building is being remediated in two stages: