This parliamentary question seeks an update on the Margaret River Perimeter Road project, including its current status, funding spent to date, and works completed in the 2015-16 financial year. The answer provides a progress report and financial breakdown.

AnsweredQoN 4248Legislative Council
Asked
16 August 2016
Portfolio
Transport

QuestionView source ↗

(1) What is the current status of the Margaret River Perimeter Road? (2) How much funding has been spent on the project to date? (3) How much funding was spent on the project in 2015-16 and what works were completed?

AnswerView source ↗

Answered
13 September 2016
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
28 days
(1) Stage 1 from Rosa Brook Road to Bussell Highway South was completed in May 2015.
Stage 2 from the northern roundabout connection to Rosa Brook Road which includes a road bridge and a foot bridge over the Margaret River and 2.2 km of John Archibald Drive is being prepared for tender in early 2017 with completion due in April 2018.
(2) $20.94 million.
(3) $6.2 million. The following works were completed:
•Geotechnical Investigations •Land purchases and advanced payments •Telstra service relocations •Western Power relocations •Preliminary road design •Concept foot bridge design •Clearing and mulching •Environmental offset payment •Fencing