Hon Alison Xamon asks about the projects included in the "Water Forever" plan, their budget, and the source of the remaining funds. Hon Helen Morton identifies groundwater replenishment and aquifer bore projects, their budget, and the Water Corporation's investment program as the source.

AnsweredQoN 1088Legislative Council
Asked
29 November 2011
Portfolio
Water

QuestionView source ↗

WATER FOREVER PLAN
I refer to the minister’s announcement of $500 million over 10 years for the “Water Forever—Whatever the weather” plan. (1) Which, if any, projects that appear in the 2011–12 budget and out years have been included as part of this plan? (2) What is the budget for those projects identified in (1)? (3) What is the source of the remainder of the $500 million announced by the minister? Hon HELEN MORTON

AnswerView source ↗

I thank the member for some notice of the question. (1) Completion of the groundwater replenishment trial and delivery of the first stage expansion; and delivery of additional confined aquifer bores. (2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
(1) Which, if any, projects that appear in the 2011–12 budget and out years have been included as part of this plan? (2) What is the budget for those projects identified in (1)? (3) What is the source of the remainder of the $500 million announced by the minister? Hon HELEN MORTON replied: I thank the member for some notice of the question. (1) Completion of the groundwater replenishment trial and delivery of the first stage expansion; and delivery of additional confined aquifer bores. (2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
(2) What is the budget for those projects identified in (1)? (3) What is the source of the remainder of the $500 million announced by the minister? Hon HELEN MORTON replied: I thank the member for some notice of the question. (1) Completion of the groundwater replenishment trial and delivery of the first stage expansion; and delivery of additional confined aquifer bores. (2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
(3) What is the source of the remainder of the $500 million announced by the minister? Hon HELEN MORTON replied: I thank the member for some notice of the question. (1) Completion of the groundwater replenishment trial and delivery of the first stage expansion; and delivery of additional confined aquifer bores. (2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
Hon HELEN MORTON replied: I thank the member for some notice of the question. (1) Completion of the groundwater replenishment trial and delivery of the first stage expansion; and delivery of additional confined aquifer bores. (2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
I thank the member for some notice of the question. (1) Completion of the groundwater replenishment trial and delivery of the first stage expansion; and delivery of additional confined aquifer bores. (2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
(1) Completion of the groundwater replenishment trial and delivery of the first stage expansion; and delivery of additional confined aquifer bores. (2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
(2) The current budget estimate for the projects identified in (1) is $147 million. (3) It is identified in the Water Corporation’s 10-year capital investment program.
(3) It is identified in the Water Corporation’s 10-year capital investment program.