❓ Question on Notice regarding the redevelopment of Port Hedland Regional Hospital, inquiring about actions taken, committees formed, and related details. The answer provides information on budget allocation, project commencement, consultant appointments, and the establishment of a Project Control Group.
AnsweredQoN 552Legislative Assembly
QuestionView source ↗
(1) Has the Health Department taken any actions aimed at the redevelopment of the Port Hedland Regional Hospital?
(2) If not, why not?
(3) If so -
(a) what action/s has/have been taken; and
(b) on what date was/were the action/s taken?
(4) Has/have any committee/s been formed for the purposes of the redevelopment of the Port Hedland Regional Hospital?
(5) If the answer to (4) is no, why not?
(6) If the answer to (4) is yes -
(a) what are the names of the committee/s;
(b) what is the purpose of the committee/s
(c) who are the members of the committee/s;
(d) which organisations are represented on the committee/s;
(e) who or what is each member of the community representing;
(f) who chose each member of the committee/s;
(g) which committee members being paid to attend committee meetings; and
(h) to whom do/does each of the committee/s report?
(7) Will the findings of any committee/s be made public?
(2) If not, why not?
(3) If so -
(a) what action/s has/have been taken; and
(b) on what date was/were the action/s taken?
(4) Has/have any committee/s been formed for the purposes of the redevelopment of the Port Hedland Regional Hospital?
(5) If the answer to (4) is no, why not?
(6) If the answer to (4) is yes -
(a) what are the names of the committee/s;
(b) what is the purpose of the committee/s
(c) who are the members of the committee/s;
(d) which organisations are represented on the committee/s;
(e) who or what is each member of the community representing;
(f) who chose each member of the committee/s;
(g) which committee members being paid to attend committee meetings; and
(h) to whom do/does each of the committee/s report?
(7) Will the findings of any committee/s be made public?
AnswerView source ↗
Answered
31 July 2001
Responded by
Minister for Health
Response time
33 days
(b) on what date was/were the action/s taken?
(b) what is the purpose of the committee/s (c) who are the members of the committee/s; (d) which organisations are represented on the committee/s; (e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(c) who are the members of the committee/s; (d) which organisations are represented on the committee/s; (e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(d) which organisations are represented on the committee/s; (e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(h) to whom do/does each of the committee/s report?
(2) Not applicable. (3) (a)-(b) $11.0m Port Hedland Hospital Redevelopment Stage 1 Project was announced in the 2000/01 State Budget on 11 May 2000. A number of urgent upgrade projects including theatres, air conditioning and staff accommodation were authorised to proceed on 20 September 2000. Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(3) (a)-(b) $11.0m Port Hedland Hospital Redevelopment Stage 1 Project was announced in the 2000/01 State Budget on 11 May 2000. A number of urgent upgrade projects including theatres, air conditioning and staff accommodation were authorised to proceed on 20 September 2000. Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
A number of urgent upgrade projects including theatres, air conditioning and staff accommodation were authorised to proceed on 20 September 2000. Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(7) No.
(b) what is the purpose of the committee/s (c) who are the members of the committee/s; (d) which organisations are represented on the committee/s; (e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(c) who are the members of the committee/s; (d) which organisations are represented on the committee/s; (e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(d) which organisations are represented on the committee/s; (e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(e) who or what is each member of the community representing; (f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(f) who chose each member of the committee/s; (g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(g) which committee members being paid to attend committee meetings; and (h) to whom do/does each of the committee/s report?
(h) to whom do/does each of the committee/s report?
(2) Not applicable. (3) (a)-(b) $11.0m Port Hedland Hospital Redevelopment Stage 1 Project was announced in the 2000/01 State Budget on 11 May 2000. A number of urgent upgrade projects including theatres, air conditioning and staff accommodation were authorised to proceed on 20 September 2000. Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(3) (a)-(b) $11.0m Port Hedland Hospital Redevelopment Stage 1 Project was announced in the 2000/01 State Budget on 11 May 2000. A number of urgent upgrade projects including theatres, air conditioning and staff accommodation were authorised to proceed on 20 September 2000. Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
A number of urgent upgrade projects including theatres, air conditioning and staff accommodation were authorised to proceed on 20 September 2000. Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
Consultants were appointed for a Strategic Planning Services Study for East Pilbara Health Service on 24 January 2001. A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
A Project Control Group was formed and its inaugural meeting was held on 26 March 2001. (4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(4) Yes. (5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(5) Not applicable. (6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(6) (a) East Pilbara Health Service Project Control Group. (b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(b) 'To bring together people with relevant expertise to provide advice and support to the General Manager in the planning for and resolution of issues that will arise during the redevelopment project of East Pilbara Health Service. The work of the Project Control Group (PCG) will, at all times, reflect consideration for best practice/benchmarking issues, so that the most cost effective and efficient outcome is achieved'. (c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(c)-(e) Kerry Mordaunt A/General Manager. East Pilbara Health Service (Chair) Karen Sullivan Secretary Geoff Anderson Pilbara Contract Consultant, Contract and Management Services Kim Audas Coordinator Western Desert Aboriginal Corporation Ian Auld Facilities Manager, Port Hedland Regional Hospital Dianne Barnett Director of Nursing, East Pilbara Health Service Dr Pascal Burton Medical Officer, Wirraka Maya Aboriginal Medical Service Chris Cottier A/Regional Manager, Aboriginal and Torres Strait Islander Commission Robyn Crane A/Chief Executive Officer, Pilbara Development Commission Ian Evans Finance Manager, East Pilbara Health Service Tony Ford Chief Executive Officer, Town of Port Hedland Mike Hartfield Consultant, Silver Thomas Hanley Architects Helen Holzwart-Jones Health Service Manager/Director of Nursing, Newman Health Service Dr Darren Keating Senior Medical Officer, Port Hedland Regional Hospital Sue McKechnie General Manager, General Health Purchasing, Health Department of Western Australia Kevin Murphy Advisor Works Program, Health Department of Western Australia Dinah Robinson Community Member, Community Development Employment Program/Claimants Region Helen Shanks Community Representative Greg Truscott Project Officer, Health Department of Western Australia (f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(f) The General Manager, East Pilbara Health Service in consultation with the Health Department of Western Australia. (g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(g) No members are paid to participate on the Project Control Group. The Health Planning Consultant attends meetings as part of the scope of his commission. (h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(h) The Project Control Group's recommendations are submitted to the Health Department of Western Australia's Strategic Infrastructure Planning Group. (7) No.
(7) No.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.