Mr. Day asks the Minister for Energy about past and proposed expenditure on transmission and distribution infrastructure maintenance from 2002 to 2009. The Minister provides a response referencing a tabled paper and the Western Power Access Arrangement.

AnsweredQoN 1722Legislative Assembly
Asked
12 December 2006
Portfolio
Energy

QuestionView source ↗

(b) maintenance of transmission and distribution infrastructure,
(ii) 30 June 2002; (iii) 30 June 2003; (iv) 30 June 2004; (v) 30 June 2005; (vi) 30 June 2006; (vii) 30 June 2007; (viii) 30 June 2008; and (ix) 30 June 2009?
(iii) 30 June 2003; (iv) 30 June 2004; (v) 30 June 2005; (vi) 30 June 2006; (vii) 30 June 2007; (viii) 30 June 2008; and (ix) 30 June 2009?
(iv) 30 June 2004; (v) 30 June 2005; (vi) 30 June 2006; (vii) 30 June 2007; (viii) 30 June 2008; and (ix) 30 June 2009?
(v) 30 June 2005; (vi) 30 June 2006; (vii) 30 June 2007; (viii) 30 June 2008; and (ix) 30 June 2009?
(vi) 30 June 2006; (vii) 30 June 2007; (viii) 30 June 2008; and (ix) 30 June 2009?
(vii) 30 June 2007; (viii) 30 June 2008; and (ix) 30 June 2009?
(viii) 30 June 2008; and (ix) 30 June 2009?
(ix) 30 June 2009?
The Minister for Energy has provided the following response: The past and proposed expenditure on Transmission and Distribution new infrastructure and maintenance works are as follows [see tabled paper no ]. The 06/07-08/09 figures are those submitted in the Western Power Access Arrangement to the Economic Regulatory Authority.
The past and proposed expenditure on Transmission and Distribution new infrastructure and maintenance works are as follows [see tabled paper no ]. The 06/07-08/09 figures are those submitted in the Western Power Access Arrangement to the Economic Regulatory Authority.

AnswerView source ↗

Answered
26 February 2007
Responded by
Minister for Energy
Response time
76 days
Answer
The Minister for Energy has provided the following response:
The past and proposed expenditure on Transmission and Distribution new infrastructure and maintenance works are as follows [see tabled paper no ]. The 06/07-08/09 figures are those submitted in the Western Power Access Arrangement to the Economic Regulatory Authority.