Hon Ray Halligan asks about the commencement and completion times for various stages of work packages related to the Southern Suburbs Railway project. The answer provides a table outlining the scope, commencement, and completion dates for each package.

AnsweredQoN 2521Legislative Council
Asked
26 October 2004
Portfolio
Planning and Infrastructure

QuestionView source ↗

(b) Stage 1 of Package D; (c) Stage 1 of Package E; (d) Stage 1 of Package F (forward works); (e) Stage 1 of Package F (remainder); (f) Stage 1 of Package B; (g) Stage 1 of Package C; (h) Stage 1 commissioning and hand-over; (i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(c) Stage 1 of Package E; (d) Stage 1 of Package F (forward works); (e) Stage 1 of Package F (remainder); (f) Stage 1 of Package B; (g) Stage 1 of Package C; (h) Stage 1 commissioning and hand-over; (i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(d) Stage 1 of Package F (forward works); (e) Stage 1 of Package F (remainder); (f) Stage 1 of Package B; (g) Stage 1 of Package C; (h) Stage 1 commissioning and hand-over; (i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(e) Stage 1 of Package F (remainder); (f) Stage 1 of Package B; (g) Stage 1 of Package C; (h) Stage 1 commissioning and hand-over; (i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(f) Stage 1 of Package B; (g) Stage 1 of Package C; (h) Stage 1 commissioning and hand-over; (i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(g) Stage 1 of Package C; (h) Stage 1 commissioning and hand-over; (i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(h) Stage 1 commissioning and hand-over; (i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(i) Stage 2 of Package A; (j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(j) Stage 2 of Package C; and (k) Stage 2 commissioning and hand-over?
(k) Stage 2 commissioning and hand-over?
The times for commencement and completion of contracts in each of the work packages for the Southern Suburbs Railway are shown below: Package Scope Commencement Completion A Railway works, civil and structures between Perth and Mandurah May 2004 December 2006 B Stations at Thomsons Lake, Thomas Road and Leda June 2005 December 2006 C Stations at Rockingham, Waikiki and Mandurah August 2005 December 2006 D Stations at Canning Bridge, Leach Hwy and South Street May 2005 December 2006 E Freeway works and bridge works at the Narrows, Canning Bridge and Mount Henry January 2004 December 2005 F City Project; tunnels and railway formation between Perth and the Narrows Bridge; Esplanade station and underground platforms to Perth station February 2004 October 2006 G Train Control and Customer Information Systems July 2003 December 2006 H Forward works and Electrical Systems integration works July 2004 December 2006 (h) & (k) The commissioning of railway systems and infrastructure will occur between October and December 2006, depending on the completion times of the different contract packages.
Package Scope Commencement Completion A Railway works, civil and structures between Perth and Mandurah May 2004 December 2006 B Stations at Thomsons Lake, Thomas Road and Leda June 2005 December 2006 C Stations at Rockingham, Waikiki and Mandurah August 2005 December 2006 D Stations at Canning Bridge, Leach Hwy and South Street May 2005 December 2006 E Freeway works and bridge works at the Narrows, Canning Bridge and Mount Henry January 2004 December 2005 F City Project; tunnels and railway formation between Perth and the Narrows Bridge; Esplanade station and underground platforms to Perth station February 2004 October 2006 G Train Control and Customer Information Systems July 2003 December 2006 H Forward works and Electrical Systems integration works July 2004 December 2006 (h) & (k) The commissioning of railway systems and infrastructure will occur between October and December 2006, depending on the completion times of the different contract packages.
(h) & (k) The commissioning of railway systems and infrastructure will occur between October and December 2006, depending on the completion times of the different contract packages.

AnswerView source ↗

Answered
23 November 2004
Responded by
Parliamentary Secretary representing the Minister for Planning and Infrastructure
Response time
28 days
(a) to (g) and (i) to (j)
The times for commencement and completion of contracts in each of the work packages for the Southern Suburbs Railway are shown below:
Package
Scope
Commencement
Completion
A
Railway works, civil and structures between Perth and Mandurah
May 2004
December 2006
B
Stations at Thomsons Lake, Thomas Road and Leda
June 2005
December 2006
C
Stations at Rockingham, Waikiki and Mandurah
August 2005
December 2006
D
Stations at Canning Bridge, Leach Hwy and South Street
May 2005
December 2006
E
Freeway works and bridge works at the Narrows, Canning Bridge and Mount Henry
January 2004
December 2005
F
City Project; tunnels and railway formation between Perth and the Narrows Bridge; Esplanade station and underground platforms to Perth station
February 2004
October 2006
G
Train Control and Customer Information Systems
July 2003
December 2006
H
Forward works and Electrical Systems integration works
July 2004
December 2006
(h) & (k) The commissioning of railway systems and infrastructure will occur between October and December 2006, depending on the completion times of the different contract packages.