❓ Hon Simon O'Brien asks about the budgeted costs of various packages within the southern rail link project, escalated to 2006-2007, as per the August 2002 Supplementary Master Plan. The Parliamentary Secretary provides the requested cost breakdowns and confirms fencing for a specific section.
AnsweredQoN 1317Legislative Council
QuestionView source ↗
Will the Parliamentary Secretary please advise, with regard to the southern rail link -
(1) The total budgeted cost of Package A, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(2) The total budgeted cost of Package B, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(3) The total budgeted cost of Package C, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(4) The total budgeted cost of Package D, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(5) The total budgeted cost of Package E, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(6) The total budgeted cost of Package F, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(7) The total budgeted cost of Package G, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(8) Will the rail trench between the Narrows Bridge and the William Street portal be fenced?
(1) The total budgeted cost of Package A, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(2) The total budgeted cost of Package B, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(3) The total budgeted cost of Package C, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(4) The total budgeted cost of Package D, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(5) The total budgeted cost of Package E, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(6) The total budgeted cost of Package F, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(7) The total budgeted cost of Package G, including escalation to 2006-2007, at the time of the release of the Supplementary Master Plan in August 2002?
(8) Will the rail trench between the Narrows Bridge and the William Street portal be fenced?
AnswerView source ↗
Answered
19 November 2003
Responded by
Parliamentary Secretary representing the Minister for Planning and Infrastructure
Response time
28 days
(1) $368.6 million (2) $19.2 million (3) $39.2 million (4) $36.7 million (5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(2) $19.2 million (3) $39.2 million (4) $36.7 million (5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(3) $39.2 million (4) $36.7 million (5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(4) $36.7 million (5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(2) $19.2 million (3) $39.2 million (4) $36.7 million (5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(3) $39.2 million (4) $36.7 million (5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(4) $36.7 million (5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(5) $112.7 million (6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(6) $245.7 million (7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(7) $11.6 million (8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
(8) Yes *It should be noted that there has been some fine-tuning of the packaging of works since that time that has slightly altered some of the current day budgets for these packages without altering the total New MetroRail Project budget of $1,419 million.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.