Hon. Samantha Rowe questions the Minister for Transport regarding delays and cost increases for the Garratt Road Bridge works in Ascot, with the Minister providing details on the scope, timeline, and budget variations.

AnsweredQoN 10Legislative Council
Asked
17 February 2015
Portfolio
Transport

QuestionView source ↗

GARRATT
ROAD BRIDGE
10. Hon SAMANTHA ROWE to the
parliamentary secretary representing the Minister for Transport:
I refer to the works being carried out by Main Roads WA on
the Garratt Road Bridge in Ascot.
(1) What is the scope of the works?
(2) What was the original completion date for the works?
(3) Has the original completion date been met or will it be
met; and, if not, why not?
(4) What is the revised completion date for the works?
(5) Will the works exceed the original amount budgeted; and,
if so, by how much?

AnswerView source ↗

I thank the honourable member for some notice of the
question.
(1) The
original scope of works included pile replacements and other minor substructure
repairs. A contract variation for footpath repairs was requested by Main Roads
for public safety reasons.
(2) The original completion date was 17 October 2014.
(3) The
original completion date of 17 October 2014 has been extended to 15 March 2015
to accommodate the footpath repair works.
(4) The contract variation works are expected to be completed
by 15 March 2015.
(5) A contract
variation of $280 000 has been issued to increase the original amount budgeted
to accommodate the additional cost of the footpath repair works.