AUGUSTA MARINA
(1) What site has the government settled on for the Augusta marina? (2) What is the estimated cost of the marina? (3) When will money be allocated to start the planning and construction stages of the marina? Hon KATE DOUST

AnswerView source ↗

On behalf of the parliamentary secretary representing the Minister for Planning and Infrastructure, I thank the member for some notice of this question. (1) In November 2004, following consideration of the community consultation, the shire requested the Department for Planning and Infrastructure to review potential developments at either Flat Rock or Dead Finish, south of Flinders Bay. (2) The estimated cost of the marina is $9.6 million. (3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.
(2) What is the estimated cost of the marina? (3) When will money be allocated to start the planning and construction stages of the marina? Hon KATE DOUST replied: On behalf of the parliamentary secretary representing the Minister for Planning and Infrastructure, I thank the member for some notice of this question. (1) In November 2004, following consideration of the community consultation, the shire requested the Department for Planning and Infrastructure to review potential developments at either Flat Rock or Dead Finish, south of Flinders Bay. (2) The estimated cost of the marina is $9.6 million. (3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.
(3) When will money be allocated to start the planning and construction stages of the marina? Hon KATE DOUST replied: On behalf of the parliamentary secretary representing the Minister for Planning and Infrastructure, I thank the member for some notice of this question. (1) In November 2004, following consideration of the community consultation, the shire requested the Department for Planning and Infrastructure to review potential developments at either Flat Rock or Dead Finish, south of Flinders Bay. (2) The estimated cost of the marina is $9.6 million. (3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.
Hon KATE DOUST replied: On behalf of the parliamentary secretary representing the Minister for Planning and Infrastructure, I thank the member for some notice of this question. (1) In November 2004, following consideration of the community consultation, the shire requested the Department for Planning and Infrastructure to review potential developments at either Flat Rock or Dead Finish, south of Flinders Bay. (2) The estimated cost of the marina is $9.6 million. (3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.
On behalf of the parliamentary secretary representing the Minister for Planning and Infrastructure, I thank the member for some notice of this question. (1) In November 2004, following consideration of the community consultation, the shire requested the Department for Planning and Infrastructure to review potential developments at either Flat Rock or Dead Finish, south of Flinders Bay. (2) The estimated cost of the marina is $9.6 million. (3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.
(1) In November 2004, following consideration of the community consultation, the shire requested the Department for Planning and Infrastructure to review potential developments at either Flat Rock or Dead Finish, south of Flinders Bay. (2) The estimated cost of the marina is $9.6 million. (3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.
(2) The estimated cost of the marina is $9.6 million. (3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.
(3) The shire sought $10 000 in funding through the recreational boating facilities scheme for 2006-07 to carry out an environmental study of the marina to establish its feasibility. The shire, as the proponent, is best placed to provide details on planning construction costs.

Explore WA Government Data