Mr. Day inquires about the status, timeline, and budget for the operating theatre upgrade and remodelling project. The response provides details on the business case finalisation, commencement and completion dates, and budget allocations for the project.

AnsweredQoN 2569Legislative Assembly
Asked
14 August 2007
Portfolio
Health

QuestionView source ↗

(a) has work commenced on the upgrade and remodelling of the operating theatre;
(i) if not, why not;
(b) if no to (a), when will work commence;
(c) what is the expected completion date;
(d) what is the total cost of the project;
(e) how much has been allocated in the 2007–2008 Budget; and
(f) how much will be allocated in the 2008–2009 Budget?

AnswerView source ↗

Answered
4 September 2007
Responded by
Minister for Health
Response time
21 days
(a) No.
i. The business case is currently being finalised.
(b) Construction is expected to commence in May 2008.
(c) Expected completion date is October 2008.
(d) $2.875M
(e) $0.5M
(f) $2.3M
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more