The question seeks information on development and building approvals delayed in several Pilbara towns due to inadequate water and sewerage infrastructure. The lack of a substantive answer suggests potential issues or a lack of readily available data.

AnsweredQoN 4119Legislative Assembly
Asked
12 October 2010
Portfolio
Water

QuestionView source ↗

What development and building approvals in Hedland, Newman, Tom Price, Karratha and Onslow have been delayed or deferred because of current limits caused by inadequate:
(a) water infrastructure, and
(b) sewerage infrastructure?

AnswerView source ↗

Answered
11 November 2010
Responded by
Minister for Water
Response time
30 days
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more