A parliamentary question regarding the cost and scope of the Margaret River infill sewerage program MR4A-3, including potential mains extensions and costs to landowners. The Minister provides estimated costs and confirms the possibility of a mains extension but cannot provide specific costs to landowners without an application.

AnsweredQoN 708Legislative Council
Asked
12 September 2006
Portfolio
Water Resources

QuestionView source ↗

INFILL SEWERAGE PROGRAM - MARGARET RIVER
(1) What is the tendered cost of the Margaret River infill sewerage program MR4A-3? (2) What is this made up of? (3) What is the cost per metre of this program, excluding the pump station and pumping mains? (4) Is there an option of a mains extension to service the 12 properties bounded by Ryans Road, Merchant Street, Hermitage Drive, Meleri Close and Railway Terrace using the rates benefits scheme? (5) If yes to (4), what will be the cost to those landowners? (6) If no to (4), why not? Hon KIM CHANCE

AnswerView source ↗

I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(2) What is this made up of? (3) What is the cost per metre of this program, excluding the pump station and pumping mains? (4) Is there an option of a mains extension to service the 12 properties bounded by Ryans Road, Merchant Street, Hermitage Drive, Meleri Close and Railway Terrace using the rates benefits scheme? (5) If yes to (4), what will be the cost to those landowners? (6) If no to (4), why not? Hon KIM CHANCE replied: I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(3) What is the cost per metre of this program, excluding the pump station and pumping mains? (4) Is there an option of a mains extension to service the 12 properties bounded by Ryans Road, Merchant Street, Hermitage Drive, Meleri Close and Railway Terrace using the rates benefits scheme? (5) If yes to (4), what will be the cost to those landowners? (6) If no to (4), why not? Hon KIM CHANCE replied: I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(4) Is there an option of a mains extension to service the 12 properties bounded by Ryans Road, Merchant Street, Hermitage Drive, Meleri Close and Railway Terrace using the rates benefits scheme? (5) If yes to (4), what will be the cost to those landowners? (6) If no to (4), why not? Hon KIM CHANCE replied: I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(5) If yes to (4), what will be the cost to those landowners? (6) If no to (4), why not? Hon KIM CHANCE replied: I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(6) If no to (4), why not? Hon KIM CHANCE replied: I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
Hon KIM CHANCE replied: I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
I thank Hon Barry House for some notice of the question. (1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(1) The estimated cost of the Margaret River infill sewerage project MR4A-3 is $1.8 million. Tenders are planned for October 2006. (2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(2) Approximately 2 000 metres of reticulation mains, a sewerage pumping station and pressure mains. (3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(3) Estimated at $500 per metre. (4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(4) Yes. (5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(5) This information is not available. The cost determination is complex and needs to be undertaken by the Water Corporation once the application is received. (6) Not applicable .
(6) Not applicable .