Mr. Wyatt asks detailed questions about the Dumas House refurbishment, including ministerial office locations, agency relocation dates, available space, and room specifications. The Minister provides specific dates and details regarding the relocation and space usage.

AnsweredQoN 7898Legislative Assembly
Asked
2 May 2012
Portfolio
Finance

QuestionView source ↗

I refer to the major refurbishment of Dumas House, and ask:
(a) which specific ministerial offices will be located at Dumas House once all ministerial offices have completed the move to their new Dumas House accommodation;
(b) what was, or is, the date by which each ministerial office is expected to be fully accommodated and functioning at Dumas House;
(c) what was, or is, the date by which the Public Sector Commission is expected to be fully accommodated and functioning at Dumas House;
(d) what was, or is, the date by which the Department of the Premier and Cabinet is expected to be fully accommodated and functioning at Dumas House;
(e) what is the name of all other government agencies which will remain accommodated at Dumas House;
(f) other than ministerial offices or government agencies, what are the name(s) of all other organisations that will remain accommodated at Dumas House;
(g) as at 1 May 2012, is there any space available for lease at Dumas House and, if so, what is the total size of this space;
(h) how many training rooms are there at Dumas House;
(i) how many meeting rooms are there at Dumas House; and
(j) what is the total size in square metres of each training and meeting room at Dumas House?

AnswerView source ↗

Answered
13 June 2012
Responded by
Minister representing the Minister for Finance
Response time
42 days
(a-b)
Minister Date of Occupation
Minister Castrilli 5 December 2011
Minister Waldron 5 December 2011
Minister Buswell 12 December 2011
Minister Morton 18 December 2011
Minister Redman 27 February 2012
Minister Grylls 27 February 2012
Minister Collier 12 March 2012
Minister O'Brien 2 April 2012
Minister Constable 2 April 2012
Minister Day 14 May 2012
Minister Johnson due 8 June 2012
Minister Porter due 20 July 2012
Minister Hames due 20 July 2012
(c) Public Sector Commission (PSC) was fully operational on 13 February 2012. In addition, PSC is expected to take delivery of its training facilities in the upper basement in June 2012.
(d) 28 May 2012
(e) Westlink, which is part of the Department of Regional Development and Lands.
(f) Not applicable.
(g) As at 1 May 2012, there is no space available for lease at Dumas House. All remaining space is undergoing refurbishment or fitout.
(h) Five
(i) Sixty-five
(j) [See tabled paper no.]
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more