A WA parliamentary question on notice regarding the Draft Residential Design Codes, inquiring about submission dates, number of submissions, analysis, and public release. The Minister provides answers regarding extensions, submission numbers, analysis by the Ministry for Planning, and indicates further public discussion is needed before finalisation.

AnsweredQoN 321Legislative Assembly
Asked
24 May 2001
Portfolio
Planning and Infrastructure

QuestionView source ↗

I refer the Minister to the Draft Residential Design Codes (“R-Codes”) released for public comment in
October 2000, and ask -
(a) was the closing date of the 25 January 2001 for public submissions extended, if so, to what date;
(b) how many public submissions were received;
(c) who is analysing the public submissions;
(d) will the public submissions be released publicly at the same time as the approval of the R-Codes;
(e) was the closing date for formal submissions by Local Councils extended, if so, to what date;
(f) how many submissions were received from Local Councils;
(g) who is analysing these submissions; and
(h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?

AnswerView source ↗

Answered
31 July 2001
Responded by
Minister for Planning and Infrastructure
Response time
68 days
(b) how many public submissions were received; (c) who is analysing the public submissions; (d) will the public submissions be released publicly at the same time as the approval of the R-Codes; (e) was the closing date for formal submissions by Local Councils extended, if so, to what date; (f) how many submissions were received from Local Councils; (g) who is analysing these submissions; and (h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?
(c) who is analysing the public submissions; (d) will the public submissions be released publicly at the same time as the approval of the R-Codes; (e) was the closing date for formal submissions by Local Councils extended, if so, to what date; (f) how many submissions were received from Local Councils; (g) who is analysing these submissions; and (h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?
(d) will the public submissions be released publicly at the same time as the approval of the R-Codes; (e) was the closing date for formal submissions by Local Councils extended, if so, to what date; (f) how many submissions were received from Local Councils; (g) who is analysing these submissions; and (h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?
(e) was the closing date for formal submissions by Local Councils extended, if so, to what date; (f) how many submissions were received from Local Councils; (g) who is analysing these submissions; and (h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?
(f) how many submissions were received from Local Councils; (g) who is analysing these submissions; and (h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?
(g) who is analysing these submissions; and (h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?
(h) will the Local Council submissions be released publicly, at the same time as the approval of the R-Codes?
(b) 111. (c) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (d) I am yet to receive the recommendations of the Western Australian Planning Commission or the R-Codes Committee on the draft R-Codes. I believe that further public discussion is required on the R-Codes prior to finalisation. (e) Yes. 28 February 2001. (f) 40 (g) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (h) See (d) above.
(c) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (d) I am yet to receive the recommendations of the Western Australian Planning Commission or the R-Codes Committee on the draft R-Codes. I believe that further public discussion is required on the R-Codes prior to finalisation. (e) Yes. 28 February 2001. (f) 40 (g) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (h) See (d) above.
(d) I am yet to receive the recommendations of the Western Australian Planning Commission or the R-Codes Committee on the draft R-Codes. I believe that further public discussion is required on the R-Codes prior to finalisation. (e) Yes. 28 February 2001. (f) 40 (g) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (h) See (d) above.
(e) Yes. 28 February 2001. (f) 40 (g) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (h) See (d) above.
(f) 40 (g) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (h) See (d) above.
(g) The Ministry for Planning has analysed submissions under the direction and guidance of the R-Codes Review Committee. (h) See (d) above.
(h) See (d) above.