Hon Ken Travers asks about the planning, timeline, and budget for the Perth to Midland Railway Line bicycle network link. The Minister provides details on planning stages, completion timeframe, cost estimation, and budget allocation.

AnsweredQoN 1831Legislative Council
Asked
21 October 2014
Portfolio
Transport

QuestionView source ↗

I refer to the Western Australia Bicycle Network Plan and ask, for the priority link Perth to Midland Railway Line from Bassendean to Midland: (a) what planning work has been done on this link; (b) what are the details of the works required; (c) when does the Minister expect work to commence; (d) when does the Minister expect works to be completed; (e) what is the estimated cost of this project; and (f) how much is currently allocated in the 2014-15 State Budget and in each year of the forward estimates?

AnswerView source ↗

Answered
3 December 2014
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
43 days
(a-b) It is proposed to install a Principal Shared Path and associated structures. Planning works include:
· concept design.
· detailed design.
· and alignment review.
(c-d)
Works are currently underway with the final section to be completed in 2017.
(e) The cost estimate for remaining works will be developed after the design has been completed.
(f) $12.63m for the current projects.